Future-Proof Healthcare
Urban Hospital, Fürth
After winning a competition, we were commissioned with the reorganization, reconstruction, and expansion of the hospital complex in three construction phases between 1980 and 2003.








Pleasant lighting, warm color scheme, and a consistent connection to the outdoor space characterize the Städtische Klinikum Fürth. In the renovation and reorganization, we placed the focus on people and their needs. The result is a relaxed, friendly building complex that radiates security and a homely atmosphere.
Renovation and expansion were carried out in three phases. In the 1st phase, the new building was designed as a greened structure with a comb-like floor plan. The main building was renovated and expanded into a care facility in the 2nd phase. The new children's clinic and the extension of the intensive care unit were done in the 3rd phase.
- Client
Städtische Kliniken Fürth
- Location
Fürth, DE
- Construction Phases
1st Phase: 1980–1989
2nd Phase: 1984–1995
3rd Phase: 2000–2003- Gross Floor Area
1st Phase: 37,700 m2
2nd Phase: 37,700 m2
3rd Phase: 8,461 m2